Ask a lawyer:
What are the standard clauses for a Construction Contract?
Table of Contents
Introduction
Standard Clauses for a Construction Contract 2.1. Definitions 2.2. Scope of Work 2.3. Time for Completion 2.4. Payment 2.5. Variations 2.6. Delays 2.7. Termination 2.8. Dispute Resolution 2.9. Insurance 2.10. Health and Safety 2.11. Intellectual Property 2.12. Force Majeure 2.13. Notices 2.14. Governing Law and Jurisdiction
Conclusion
Introduction
This response will outline the standard clauses typically found in a construction contract in Kenya. These clauses are essential for defining the rights and obligations of the parties involved, ensuring a smooth and successful construction project.
Standard Clauses for a Construction Contract
2.1. Definitions
The contract should clearly define key terms used throughout the document. This includes:
"Contractor": The party responsible for carrying out the construction work.
"Employer": The party commissioning the construction work.
"Works": The construction project being undertaken.
"Contract Documents": All documents forming part of the contract, including the agreement, specifications, drawings, and other relevant documents.
"Variation": Any change to the scope of work, time for completion, or payment terms.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.2. Scope of Work
This clause defines the specific construction work to be undertaken by the Contractor. It should include:
Detailed description of the project: This should be comprehensive and include all aspects of the construction work, including materials, specifications, and standards.
Drawings and specifications: The contract should reference the relevant drawings and specifications that form part of the project.
Exclusions: Any work not included in the scope of work should be clearly stated.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.3. Time for Completion
This clause sets out the agreed-upon timeframe for completing the construction work. It should include:
Commencement date: The date on which the Contractor is expected to begin work.
Completion date: The date by which the Contractor is expected to complete the work.
Extension of time: Provisions for extending the completion date due to unforeseen circumstances, such as delays caused by the Employer or force majeure events.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.4. Payment
This clause outlines the payment terms for the construction work. It should include:
Payment schedule: A detailed breakdown of the payments to be made to the Contractor, including the amounts, milestones, and payment dates.
Retention: A percentage of the payment may be withheld by the Employer until the completion of the project, as a form of security.
Interest: Provisions for interest on late payments.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.5. Variations
This clause addresses changes to the scope of work during the construction process. It should include:
Procedure for variations: A clear process for requesting, approving, and implementing variations.
Valuation of variations: A method for determining the cost of variations, including labor, materials, and other expenses.
Time extensions: Provisions for extending the completion date due to variations.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.6. Delays
This clause addresses delays in the construction project. It should include:
Causes of delay: Identifying the different types of delays, such as those caused by the Employer, the Contractor, or unforeseen circumstances.
Notice requirements: Procedures for notifying the other party of any delays.
Extension of time: Provisions for extending the completion date due to delays.
Liquidated damages: Penalties for exceeding the completion date, if applicable.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.7. Termination
This clause outlines the circumstances under which the contract can be terminated. It should include:
Termination by the Employer: Reasons for termination by the Employer, such as breach of contract by the Contractor or failure to meet deadlines.
Termination by the Contractor: Reasons for termination by the Contractor, such as non-payment by the Employer or changes to the scope of work.
Consequences of termination: The procedures and consequences of termination, including payment obligations and the disposition of the works.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.8. Dispute Resolution
This clause outlines the process for resolving disputes that may arise during the construction project. It should include:
Negotiation: A requirement for the parties to attempt to resolve disputes through negotiation.
Arbitration: A provision for resolving disputes through arbitration, if negotiation fails.
Jurisdiction: The jurisdiction in which any disputes will be resolved.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.9. Insurance
This clause addresses insurance requirements for the construction project. It should include:
Contractor's insurance: The Contractor should maintain adequate insurance coverage for liability, property damage, and workers' compensation.
Employer's insurance: The Employer may also require insurance coverage for specific risks, such as damage to existing property.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.10. Health and Safety
This clause addresses health and safety requirements for the construction project. It should include:
Compliance with regulations: The Contractor should comply with all applicable health and safety regulations in Kenya.
Safety procedures: The Contractor should implement appropriate safety procedures on the construction site.
Risk assessments: The Contractor should conduct risk assessments to identify and mitigate potential hazards.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.11. Intellectual Property
This clause addresses intellectual property rights related to the construction project. It should include:
Ownership of designs: The ownership of any designs or plans created for the project.
Use of intellectual property: The rights of the parties to use intellectual property created for the project.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.12. Force Majeure
This clause addresses events beyond the control of the parties that may affect the construction project. It should include:
Definition of force majeure events: Examples of force majeure events, such as natural disasters, war, or government regulations.
Consequences of force majeure events: The impact of force majeure events on the contract, including potential delays and extensions of time.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.13. Notices
This clause outlines the procedures for providing notices between the parties. It should include:
Method of delivery: The methods for delivering notices, such as email, registered mail, or courier.
Effective date: The date on which notices are deemed to be received.
Source: This section is based on general principles of contract law and best practices in construction contracts.
2.14. Governing Law and Jurisdiction
This clause specifies the governing law and jurisdiction for resolving disputes. It should include:
Governing law: The law that will govern the contract, such as Kenyan law.
Jurisdiction: The court or tribunal that will have jurisdiction over any disputes.
Source: This section is based on general principles of contract law and best practices in construction contracts.
Conclusion
The standard clauses outlined above are essential for a comprehensive and legally sound construction contract in Kenya. By including these clauses, the parties can ensure a clear understanding of their rights and obligations, minimize the risk of disputes, and promote a successful construction project. It is important to note that this is not an exhaustive list, and specific clauses may need to be tailored to the specific requirements of each project. Consulting with a legal professional is recommended to ensure that the contract is drafted appropriately and meets the needs of all parties involved.
Answered by mwakili.com